Build log date: Friday, January 23, 2004
-
Match drilling the radio stack brackets to the panel.

-
A bit of scotchbrite action was needed to let the garmin tray fit into the radio stack opening.

-
Just making sure the radio fits in the opening.

-
I've just match drilled a couple of rivet holes in the switch panel for the angle that mounts it to PA-1 stiffener.

-
Cutting openings for the vents into the switch panel bracket.

-
Drilling the switch panel brackets for the skin holes. Later I installed these brackets then match drilled these holes into the skin.

-
I don't remember what I was doing in this picture, but damn that is a nice job of riveting.

-
Drilling #40 holes in the switch panel stiffener for the rivets that will hold this stiffener to the panel.

-
Match drilling the stiffener to the switch sub panel.

-
Not a bad job of riveting. I've learned that for best apperances you should err on the side of countersinking a bit too deep rather than too shallow.